Brush High School

Brush, Colorado

 

Project Description

Western Engineering Consultants (WEC) was retained to provide Storm Water Management services for the Brush High School Expansion. A new auxiliary gym, weight room, wrestling room, restrooms, and supporting amenities in addition to a new parking lot and revised access necessitated a State Storm Water Management Plan and Report as required for State permitting. WEC provided the report and plan in a quick turnaround in order to keep the High School Expansion project on schedule.

 

Highlights

Engineering Services - SWMP necessary to complete expansion

Project Cost

$1,200 Consulting
$250,000 Construction

Client

The Neenan Company

 

 

If you have additional questions regarding our services or if you would like to schedule a meeting, please give us a call at 720-685-9951.